June 6, 2023

Steve Vick International (SVI) recently carried out a project for JN Bentley on behalf of Yorkshire Water. The project involved filling with cementitious grout a 180-metre length of 300mm diameter abandoned sewer pipes. SVI's Contract Service teams are known for providing on-site solutions to a wide variety of pipe decommissioning and renewal problems, and the project for Yorkshire Water was no...

March 6, 2023

The Steve Vick International Contract Services team recently assisted Anglian Water, through JN Bentley, in a project which involved building a new network of interconnecting water pipelines from Lincoln to Grantham. The 34 km section starts south of Lincoln, near Waddington, and ends near Harrowby, east of Grantham. This project is part of a bigger project with Anglian Water to create...

January 18, 2022

Steve Vick International’s Contract Service team were recently asked to assist in filling a section of decommissioned fuel pipeline.  The pipeline was situated beside a canal bridge in Staffordshire. W B Civil & Mechanical Ltd was carrying out a project which involved diverting a 10” diameter fuel line and decommissioning a section of it which was 380 metres in length.  The pipeline...

Steve Vick International’s (SVI) Contract Service team assisted Cadent with a Live Riser Transfer project at Shropshire House in North London. Following a survey of the high-rise block of flats, carried out by Cadent, severe corrosion was identified on the inlet supply at the base of the riser, just above ground level.  Cadent immediately started planning the best method of remedying to...

October 4, 2021

Steve Vick International assisted JDT Utilities in decommissioning a 180m stretch of 18” intermediate pressure steel gas pipeline (running at 7Bar pressure). The abandoned main, prior to diversion and decommissioning, supplied the whole of Surrey Quays. Part of a larger fifteen-year regeneration project, of a five acre site, the pipe was required to be decommissioned following commission of...

September 23, 2021

Contract Service teams from Steve Vick International recently carried out a project for a gas distribution company which involved filling with cementitious grout a 115 metre length of 36” diameter medium pressure gas main. The decommissioned main in Beddington Lane, Croydon, had been inserted with 630mm PE as part of the gas distribution network’s mains replacement programme in the area....

February 9, 2021

Steve Vick International’s ground-breaking FOAMBAG Operation on Stubs (FBOS) technique, is the long awaited solution for fully decommissioning mains of engineering difficulty, such as stranded, one way fed, stubs or those found on mains replacement schemes. The FBOS technique fully decommissions mains right up to the last transition joint on mains of 4”-6” in diameter. These sections of...

August 4, 2020

The Steve Vick International Contract Service team recently assisted gas distribution company SGN on a project to divert a gas main across the Caledonian Canal near Loch Ness. The project required the new gas reinforcement main to be laid under the Caledonian Canal at Torvean, Inverness. This project, due to the complexity of the canal crossing, had been delayed while other options were...

July 7, 2020

Laing O’Rourke has recently recruited Steve Vick International’s (SVI) Contract Service team to carry out crucial time saving cutting operations using the Keel Cutter as part of a major project to develop three wastewater treatment works in Lancashire. The improvements at United Utilities Waste Water Treatment Works at Blackburn, Darwen and Nab’s Head, collectively known as the Blackburn...

February 13, 2017

Steve Vick International’s (SVI) Contract Service team have renewed ten 1.5” live gas risers in multi storey buildings in an affluent suburb of Leeds, without the need to decommission the services whilst the work was in progress. Using their Live Gas Riser Transfer technique, SVI were able to offer Northern Gas Networks (NGN) a service that kept external pipework to a minimum and thus...

November 15, 2016

As part of National Grid’s major gas mains replacement project on Stanley Bridge, King’s Road, London, a Steve Vick International Contract Service team was recently appointed to seal off the ends of three 36” abandoned cast iron mains and one 36” steel main. The filling process took just four hours to complete. The voids needed to be sealed off to prevent backfill entering the open...

October 10, 2016

The Steve Vick International (SVI) Contract Service was recently contacted by SGN to help carry out a gas mains renewal on South Street, Chichester. The Live Mains Insertion (LMI) method was pioneered by SVI in 1981. It was chosen by SGN for this replacement project because closing the street was not an option. The busy street comprises commercial businesses as well as significant pedestrian...