Isle of Man – Stromstopp 2 X 22″ Gasnetz

A Special Contracts Team from Steve Vick International recently carried out a flow stopping project for Manx Gas on two 22” gas mains in Douglas, Isle of Man. Das Hotel liegt am South Quay, nahe an einem Gasbehälter, das 200 meter Abschnitte von Zwei-Wegen zugeführt Haupt wurden aufgegeben werden, so daß Governors, um in ein Mitteldrucksystem verbinden installiert werden kann.

Zwei x Zwei-Wege-Strom Stop-Betrieb, mit insgesamt acht Taschen, were carried out by a two-man team using the FOAMBAG™ technique, von Steve Vick Internationale entwickelt. The Foam Bags were introduced into each of the live mains, either side of the cut-off points, via standpipes installed into 2” tappings through standard Wask bases.

The bags are constructed of semi-porous fabric and have an integral steel support bar to which a nylon fill tube is fitted. Through this an expanding resin foam is introduced using a mix and inject machine. Due to the large diameter of this main, the bags were of a double-skin construction. The inner bags were filled initially and allowed to cure before the outer bags were filled. On full expansion, some of the foam seeps through the bag to adhere to the surface of the main creating a more effective seal.

The flow stopping project took half a day to complete. Filling of the Foam Bags™ began at 09.00 and was completed by 10.30. By 14.30, the main had been cut and capped.

Billy Hay, Distribution Manager for Manx Gas, reported that the job went perfectly. “Using conventional, mechanical flow stopping methods would have cost far more than the Foam Bag™ operation,” he said.

 

Erscheinungsdatum – 13Oktober 2006

Teile diesen Artikel: